101.4          Does the 2009 IECC apply?

101.4.2       Historic Exemption

101.4.3       Applicable Property  New Construction –  Remodel –  Finishout – Addition

101.4.4       A Change in Occupancy

101.4.5       A Change in space conditioning

303            Material Identification

303.1.1.1     Attic insulation depth marker every 300 sqft for blown in insulation

303.1.3       Fenestration product rating on every window with U – factor and SHGC

303.2          Insulation installation to manufacturer’s instructions and IBC

400            Residential buildings

401.3          Certificate posted on /in electrical panel with system R or U values of system components, SHGC  and mechanical efficiencies

402.1.1       Prescriptive requirements for assembly components

                  Fenestration                            U – Factor            ≤  0.50

                  Skylight                                  U – Factor            ≤ 0.65

                  Solar Heat Gain Coefficient      SHGC value          ≤ 0.30

                  Ceiling                                    R – value              R – 30

                  Walls                                      R – value              R – 13

                  Floors                                     R – value              R – 19

                  Crawlspace / Basement            R value                R – 5 continuous R – 13 batt

402.2.3      Access hatches and Doors weather stripped and insulated to attic value

402.3         Fenestration exemptions

402.3.3      Glazed fenestration exemption – one side hinged door up to 15 sqft

402.3.4      Opaque door exemption – one side hinged door up to 24 sqft

402.3.6      Glass replacement only exemption

402.4.1      Building Thermal Envelope durably sealed to limit infiltration

                 Caulked, gasketed or weather stripped on all;

                 Wall top plate penetrations sealed on all walls

                 Seal bottom plate  to foundation / vertical wall intersections on exterior walls        

                 Seal around Windows & Doors & all Building envelope penetrations

                 Seal or gasket Doors / Windows / Fixtures / Junction boxes for outlets & switches

402.4.2      Air sealing and insulation inspection

                 See Table 402.4.2 for component list

402.4.2.1   Testing Option  

                 Blower door test performed @ 50 pascals    7 ACH max        OR

402.4.2.2   Visual inspection Option

                 Onsite inspections after insulation installed (Floors / Walls / Attic)

                 & before insulation covered by sheetrock (Walls)

402.4.3      Fireplaces

                 Gasketed doors & outdoor combustion air required

402.4.4      Fenestration air leakage

                  Windows, skylights & sliding glass doors             < 0.3 cfm/sqft

                  Swinging doors                                                  < 0.50 cfm/sqft

402.4.5      Recessed Lights

                 IC rated & Air tight       (<2 cfm @ 75 Pa)

403 Systems

403.1.1      Programmable thermostat – 1 per dwelling required

403.2.1      Duct Insulation

                 Unconditioned attic         R – 8 supply & R – 6 return

403.2.2      Duct sealing to made substantially airtight by means of tapes, mastics, liquid sealants, gasketing or other approved closure systems

                 Duct tightness verification required (@ 25 Pa)

                           1.    Post construction  test  ≤ 12 cfm / 100 sqft of conditioned area with all registers taped closed

                           2.    Rough-in test  ≤ 6 cfm / 100 sqft of conditioned area with all registers taped closed or 4 cfm / sqft if no air handler installed

403.2.3      Building cavities may not be used as supply ducts

403.3         Mechanical system piping requires R – 3 insulation if carrying fluids above 105° or below 55°

403.4         Circulating hot water piping requires R – 2 insulation on hot supply and return piping. Also requires automatic switch or readily accessible switch to control system

403.6         Manual J calculations required for HVAC system sizing

404.1         Lighting Requirement 50% of lamps are high efficacy lamps (CFL)